Configure a Direct Debit dunning schedule
Direct Debit lets you specify, for each dunning step after Day 1, whether to retry the payment, send an email, or both. A Day 1 step always retries the payment. This means you can notify Customers of a payment failure by email without also retrying payment, to avoid additional gateway transaction fees.
To configure a Direct Debit dunning schedule
- Go to Config > Retries & Dunning, then select Create Schedule.
- Under Dunning Type, select Direct Debit.
- Build a custom strategy, or select Use Template to start from the Basic or Assertive template.

Set the retry interval
Due to Direct Debit processing time, the minimum interval between retry attempts is 5 days.
When editing or adding a step, you can:
- Specify the day it executes.
- Enable or disable retrying the payment.
- Enable or disable sending an email, and configure its template.
Configure the Final Action
The last step in a Direct Debit schedule is its Final Action. The Final Action can't retry payment and must be either Cancel Subscription or Mark as Unpaid; if you need to notify the Customer at this step, use email only.
Select the day Advanced Billing takes the Final Action, then choose:
- Cancel Subscription: The Subscription transitions to the Canceled state and stops accruing new charges. No more attempts are made to collect the balance due. A canceled Subscription can be reactivated later using the Retry/Reactivate action.
- Mark as Unpaid: The Subscription transitions to the Unpaid state but continues to accrue new charges. No more attempts are made to collect the balance due. An unpaid Subscription can be moved back to Active by recording a payment, retrying the renewal and receiving a successful payment, or zeroing out the balance and retrying the renewal.

Dunning emails
Each step in the schedule can send an email notification. Select Edit on a step, then move the Send Email slider to on to launch the email editor. Within the email editor, you can customize the subject and body of the email. You can also create a custom layout to personalize the look and feel of the email.

To BCC yourself on a given step's email, check Email BCC List for that step.